STAGE-TECH was tasked with refurbishing and then assembling a 65' tall custom Christmas Tree for a multi year contra
ct at the Venetian Hotel in LAS VEGAS. The structure was not designed or fabricated by Stage-tech so preparing for the onsite build required hundreds of hours of time to mock up the unit to limit issues that might arise onsite. The structure incorporated over 900 acrylic balls, 3000+ R5 Lights and 120+ DMX controlled IP65 LED lights . All in all the unit and it's fixings took 1000+ man hours to build and remove. Aside from all of the hard work and preparations some good memories were had along the way. See more below on that!
• Rendering of skeleton build
• Pre fab & load in commences
Fun.
Work & Fun
• Video Clip
This project had a Great team!!
Thank you to all involved: Charley Guest -CAD Designs & Project Manager Charley Guest - Account manager
Dave Broadhead - Rigging Lead
Kenny Kightlinger - Rigging Lead
Ben Erlich - Rigging Tech
Tyler Guest - Rigging Tech
Mike Jacobsen - Big Ball Tech
Phil Johnson - Lighting Tech
Jason Mansell - Lighting Tech